Technical Articles
M/s Uttar Banga Sambad is a regional Bengali daily newspaper published in the state of west Bengal, India. The case study presents harmonic analysis at this newspaper printing press.
The printing press, a drive based system (both AC and DC drives) is the major load in the factory and the major source of harmonics. The problem experienced was high current harmonics i.e. about 36.8% and consequent voltage harmonics of about 9.5%. As a result the customer experienced a poor power factor, and frequent tripping of circuit breakers of capacitor bank (due to high VTHD) leading to loss of incentive from electricity board.
This case study is presented in 4 different parts followed by the conclusions. The four parts are as follows:
Part I - Harmonic study.
The initial harmonic analysis results were as below.
1. Harmonic Analysis was carried out at main LV incomer of 500KVA 11KV/433 V transformer.
2. 140 kVAr APFC Panel is installed at site (without detuned reactor)
3. Harmonic levels with capacitors ON and OFF were recorded.
a. With APFC On: VTHD = 9.5%; ITHD = 36%
b. With APFC Off: VTHD = 8%; ITHD = 22%
The following figures are of harmonic study with APFC panel ON.
5th and 7th harmonic are dominant due to AC Drives & 11th harmonic is dominant dut to the Presence of DC drives
From Figure 6 that the displacement power factor is 0.944 and the true power factor is 0.882. (True PF = Displacement PF X Distortion PF). In this case harmonics are responsible for low distortion PF leading to lower value of true PF
Considering observed harmonic level, it was decided to install AHF at site. Sizing decisions were done as follows
Part II — AHF sizing and installation
The summary of the conducted harmonic study prior to AHF installation is as follows:
The actual AHF sizing can be calculated using the "Active Harmonic Filter Selection Tool" in etaPRO v3.O as indicated below. (etaPRO v3.0 can be downloaded from www.Lntebg.com/etaPRO)
It can be inferred from above software selection tool that a 300A, AHF is required for the considered input parameters
The Printing press load is a complete non linear load responsible for harmonic production. Aux load is the auxiliary load which mainly includes lighting fans etc.
Part III - Harmonic Study after AHF Installation.
A300 A, 3 phase 3 wire AHF was installed and following results were obtained.
It can be observed from Figure 13 that the load current waveform is much smoother than the before (Figure 5)
Due to reduction in harmonics, distortion PF has increased leading to the increase in the overall PF to 0.946, indicating distortion PF
Part IV - Tariff System & Bill Comparison
The West Bengal Electricity Board has kWh billing and penalty/ Incentive rates applicable as follows:
11 kV Industrial Consumer E (Bt) type tariff system
| E (Bt) TYPE OF CONSUMERS | Energy Charge P/kWh (Winter) | Demand Charges (Rs./KVA/month) | |||
| Normal TOD | 06.00 hrs-17.00 hrs | All Units | Normal | 707 | 384 |
| 17.00 hrs-23.00 hrs | All Units | Peak | 849 | ||
| 23.00 Hrs-06.00Hrs. | All Units | Off-Peak | 530 | ||
Power factor Incentive Scheme Applicable
| SLAB | Power Factor (PF) | Power Factor Rebate & surcharge On Energy Charge in Percentage for the Year 2015-16 | ||
| Range | For Consumers Under TOD Tariff | |||
| Normal Period (6.00 AM to 5.00 PM) | Peak Period (5.00 PM to 11.00PM) | OH-Peak Period (11.00 PM to 6.00 PM) | ||
| PF > 0.99 | -8 | -9 | -6 | |
| Slab 1 | PF > 0.98 & PF = ≤ 0.99 | -7 | -8 | -5 |
| Slab 2 | PF > 0.97 & PF = ≤ 0.98 | -5 | -6 | -4 |
| Slab 3 | PF > 0.96 & PF = ≤ 0.97 | -4 | -5 | -3 |
| Slab 4 | PF > 0.95 & PF = ≤ 0.96 | -3 | -4 | -2 |
| Slab 5 | PF > 0.94 & PF = ≤ 0.95 | -2.25 | -3 | -1.5 |
| Slab 6 | PF > 0.93 & PF = ≤ 0.94 | -1.5 | -2 | -1 |
| Slab 7 | PF > 0.92 & PF = ≤ 0.93 | -0.75 | -1 | -0.05 |
| Slab 8 | PF > 0.86 & PF = ≤ 0.92 | 0 | 0 | 0 |
| *Yellow Highlights indicate reference slabs as indicated in bill analysis below | ||||
The following section is the comparison of the bills of the month of July and September in order to evaluate the savings post AHF installation. The bill calculations are presented and actual bills are attached for the reader's reference. The first major column indicates the parameter and side by side comparison for the months of July and September with APFC Panel Switched ON.
| APFC Panel Only | APFC Panel + AHF | |||||
| Parameter | July | September | ||||
| Supply Voltage | 11 kV | 11 kV | ||||
| Contract Demand | 415 kVA | 415 kVA | ||||
| Fixed Demand charges (Rs./kVA) | 384 | 384 | ||||
| Percentage Chargeable | 85% | 85% | ||||
| Power Factor | 0.8916 | 0.9743 | ||||
| Meter Reading | MVAH | |||||
| Time | Normal | Peak | Off-Peak | Normal | Peak | Off-Peak |
| Present Reading | 417.77 | 527.26 | 1890.82 | 441.04 | 556.44 | 1991.6 |
| Previous Reading | 405.84 | 512.78 | 1830.66 | 429.9 | 543.35 | 1944.1 |
| Units Consumed (MVAh) | 11.93 | 14.48 | 60.16 | 11.14 | 13.09 | 47.5 |
| Net MF | 500 | 500 | 500 | 500 | 500 | 500 |
| kVAh (Units Consumed * MF) | 5965 | 7240 | 30080 | 5570 | 6545 | 23725 |
The conclusions that can be drawn out from the harmonic study are as follows:-
The results of AHF installation can be seen from the electricity bill also. Following are the main observations.
The AHF can be used to improve the PF further to unity such that the percentage rebate for all times of day falls in Slab-1 as indicated by PF Incentive Scheme Table.
Additional savings of INR 4457 can be obtained from the same.
From the difference in the bill it can be seen than, the customer has a saving of INR 54768/ month (average). The 300 A AHF panel has an approximate cost of INR 10,00,000. Hence the payback period is 19 months. The same can be further be reduced if power factor is made unity.
Sourav Dasmodak,
Product Management & Marketing (Powergear - ACB)Product Owner of Air Circuit Breaker (ACB) of Lauritz Knudsen for Domestic & International Market. I can talk to you about Electrical Products' Sales, Business Development, Market Expansion, Cracking Critical Strategic Account, handling Key Account & of course how to develop & motivate Channels along with the organizational growth. Having near about one and a half decade of experience across the country with major electrical manufacturers (Top 4).